Tom was on vacation for the last two weeks and feels like we got a lot accomplished:
* Front of building painted
* Landscaping and painting done on side of building
* Other half of floor prepped for sanding, and some edging done
* Priming of ceiling and walls begun
* Slab roller for the pottery studio purchased
* Outside of ductwork being cleaned
 |
30 or 40 years of dirt and nicotine stains coming of with Windex, Magic
Erasers and LOTS of elbow grease |
* Support beams in basement are prepped to be repaired/replaced
 |
Our contractor cut around the beam and is going to lift
the concrete out and check what's under the slab. He
has a feeling it's water. Bottom of water-damaged beam will
be cut and replaced with a concrete mold. |